[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106088":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106088,781,2,"多选题","关于隧道开挖施工，以下说法正确的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","全断面法可用于Ⅰ～Ⅲ级围岩的中小跨度隧道",true,{"key":16,"text":17,"correct":14},"B","台阶法可用于Ⅲ～Ⅳ级围岩的中小跨度隧道。",{"key":19,"text":20,"correct":14},"C","开挖方法包括环形开挖留核心土法、中隔壁法、双侧壁导坑法及中导洞法",{"key":22,"text":23,"correct":14},"D","应根据隧道长度、断面大小、结构形式、工期要求、机械设备、地质条件等，选择适宜的开挖方案",{"key":25,"text":26,"correct":27},"E","隧道洞口锚喷加固按坡面开挖顺序由下往上实施",false,"ABCD","本题考查的是隧道开挖施工质量监理。锚喷加固应按坡面开挖顺序由上至下分段实施，一般为先锚后喷或挂网后再喷。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]