[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106076":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106076,781,2,"多选题","对于多年冻土地基的处理，下列规定正确的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","严禁地表水流入基坑",true,{"key":16,"text":17,"correct":14},"B","及时排除季节冻层内的地下水",{"key":19,"text":20,"correct":14},"C","及时排除冻土本身的融化水",{"key":22,"text":23,"correct":14},"D","搭设遮阳棚和防雨棚",{"key":25,"text":26,"correct":27},"E","做好的基础应等待数日后，再回填封闭",false,"ABCD","多年冻土地基的基础不应置于季节冻融土层上，并不得直接与冻土接触；基础的基底修筑于多年冻土层（即永冻土）上时，基底之上应设置隔温层或保温层材料，且铺筑宽度应在基础外缘加宽1m；按保持冻结的原则设计的明挖基础，其多年平均地温等于或高于－3℃时，应于冬季施工；多年平均地温低于－3℃时，可在其他季节施工，但应避开高温季节，并应按下列规定处理：①严禁地表水流入基坑。②及时排除季节冻层内的地下水和冻土本身的融化水。③必须搭设遮阳棚和防雨棚。④施工前做好充分准备，组织快速施工。做好的基础应立即回填封闭，不宜间歇。必须间歇时，应以草袋、棉絮等加以覆盖，防止热量侵入。施工时，明水应在距坑顶10m之外修排水沟。水沟中水应引流远离坑顶并及时排除融化水。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]