[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106074":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106074,781,2,"多选题","关于后张法预应力的施工，正确的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","所有设备应最少每间隔两个月进行一次检查",true,{"key":16,"text":17,"correct":14},"B","使用时间超过6个月，张拉设备应重新进行校验",{"key":19,"text":20,"correct":14},"C","张拉次数超过300次，张拉设备应重新进行校验",{"key":22,"text":23,"correct":14},"D","千斤顶检修或更换配件后，张拉设备应重新进行校验",{"key":25,"text":26,"correct":27},"E","施工人员更换后，张拉设备应重新进行校验",false,"ABCD","本题考查的是桥梁工程上部构造施工质量监理。预应力张拉中。如发现下列任何一种情况，张拉设备应重新进行校验：使用时间超过6个月；张拉次数超过300次；使用过程中千斤顶或压力表出现异常情况；千斤顶检修或更换配件后。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]