[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106067":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106067,781,2,"多选题","悬臂浇筑前，需要根据哪些荷载（ ），设置预拱度。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","1\u002F2静活载挠度",true,{"key":16,"text":17,"correct":14},"B","各梁段的重量引起的挠度",{"key":19,"text":20,"correct":14},"C","混凝土的收缩与徐变引起的挠度",{"key":22,"text":23,"correct":14},"D","施工设备荷载引起的挠度",{"key":25,"text":26,"correct":27},"E","降雨引起的挠度",false,"ABCD","本题考查的是桥梁工程上部构造施工质量监理。悬臂浇筑前，各施工阶段的弹、塑性挠度（包括待浇及后浇各梁段的重量、预应力、混凝土的收缩与徐变、施工设备荷载、桥面系恒载、体系转换引起的挠度）及1\u002F2静活载挠度，设置预拱度。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]