[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106041":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106041,781,2,"多选题","沥青混合料的摊铺，正确的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","在摊铺之前，对下层进行检查",true,{"key":16,"text":17,"correct":14},"B","在开始摊铺混合料时，应考虑在路面边缘设置路缘石（拦水带）的具体位置、埋设深度",{"key":19,"text":20,"correct":14},"C","为消除纵向接缝，应采用全路摊铺",{"key":22,"text":23,"correct":14},"D","摊铺温度不低于125℃，但不得超过160℃",{"key":25,"text":26,"correct":27},"E","禁止采用人工铺筑混合料",false,"ABCD","本题考查的是沥青面层施工质量监理。选项E错误，对外形不规则，路面厚度不同，空间受到限制以及人工构造物接头等摊铺机无法工作的地方，经监理工程师批准可以采用人工铺筑混合料。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]