[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106028":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106028,781,2,"多选题","关于基层（底基层）施工阶段的碾压质量，正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","直线段，由两侧向中心碾压",true,{"key":16,"text":17,"correct":14},"B","超高段，由内侧向外侧碾压",{"key":19,"text":20,"correct":14},"C","碾压过程中，混合料的表面应始终保持潮湿",{"key":22,"text":23,"correct":24},"D","压路机可以在已完成的路段上掉头",false,{"key":26,"text":27,"correct":14},"E","施工中，从加水拌和到碾压终了的延迟时间不应超过规定要求","ABCE","本题考查的是路面基层（底基层）施工质量监理。选项D错误，严禁压路机在已完成的或正在碾压的路段上掉头和紧急制动，以保证结构层表面不受破坏。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]