[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106008":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106008,781,2,"多选题","填土路基的基本要求有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","分段填筑、分层碾压",true,{"key":16,"text":17,"correct":14},"B","不同性质的填料，不得混填",{"key":19,"text":20,"correct":14},"C","透水性差的土上铺设透水性好的土，设置横坡",{"key":22,"text":23,"correct":24},"D","不同高度的土基填筑时，可从任意高度开始填筑",false,{"key":26,"text":27,"correct":24},"E","土方填筑无需搭接","ABC","本题考查的是一般路基施工质量监理。选项D错误，路堤填筑时，应从最低处起分层填筑，逐层压实。选项E错误，填方分几个作业段施工时，接头部位如不能交替填筑,先填路段应按1:1～1:2坡度分层留台阶；如能交替填筑，应分层相互交替搭接,搭接长度应不小于2m。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]