[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106004":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106004,781,2,"多选题","下列需要做路基填方工程试验路段的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","采用四新技术的路基",true,{"key":16,"text":17,"correct":14},"B","特殊填料路堤",{"key":19,"text":20,"correct":14},"C","填石路堤、土石路堤",{"key":22,"text":23,"correct":14},"D","二级及二级以上公路路堤",{"key":25,"text":26,"correct":27},"E","三级公路的路堤",false,"ABCD","本题考查的是路基工程概述。下列情况需要做试验段：二级及二级以上公路路堤；填石路堤、土石路堤；特殊填料路堤；特殊路基；拟采用新技术、新工艺、新材料、新设备的路基；其他监理工程师指示需要试验段的路基。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（交通工程）","建筑工程",0]