[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105966":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105966,781,1,"单选题","凡征占地面积在（ ）以上或者挖填土石方总量在10000m3以上的开发建设项目，应当编报水土保持方案报告书;其他开发建设项目应当编报水土保持方案报告表。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1hm2",true,{"key":16,"text":17,"correct":18},"B","2hm2",false,{"key":20,"text":21,"correct":18},"C","5000㎡",{"key":23,"text":24,"correct":18},"D","8000㎡","凡征占地面积在1hm2(即10000m2)以上或者挖填土石方总量在10000m3以上的开发建设项目，应当编报水土保持方案报告书;其他开发建设项目应当编报水土保持方案报告表。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]