[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105930":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105930,781,1,"单选题","膨胀岩土地质隧道施工符合的规定错误的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","除常规监测项目外，尚应加强监测围岩净空位移、围岩压力，并应根据监测结果及时调整预留变形量和支护参数不得。",false,{"key":16,"text":17,"correct":18},"B","分部开挖可超前独进",true,{"key":20,"text":21,"correct":14},"C","隧道开挖断面轮廓应圆顺",{"key":23,"text":24,"correct":14},"D","岩面不得受水浸泡。","膨胀岩土地质隧道施工应符合下列规定： ①施工前应查明膨胀岩土岩性、规模、各向异性程度、吸水性、围岩强度比、水文地质、膨胀机理等情况，选择合适的施工方法和预控措施。 ②除常规监测项目外，尚应加强监测围岩净空位移、围岩压力，并应根据监测结果及时调整预留变形量和支护参数。 ③应控制开挖循环进尺,逐次开挖断面各分部，分部开挖不得超前独进。 ④隧道开挖断面轮廓应圆顺。 ⑤隧道开挖后应尽快初喷混凝土封闭岩面,并应控制施工用水,加强施工用水管理，岩面不得受水浸泡。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]