[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105890":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1105890,781,1,"单选题","下列选项不属于现场处置方案内容的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","事故报告程序和责任人",false,{"key":16,"text":17,"correct":14},"B","所有单位的应急过程所遵循的指挥与配合原则",{"key":19,"text":20,"correct":21},"C","核查现场应急处置方案编制内容是否齐全",true,{"key":23,"text":24,"correct":14},"D","确定可能发生的安全事故类型","现场处置方案内容包括：①编制依据；②确定可能发生的安全事故类型；③应急救援原则；④事故报告程序和责任人；⑤事故现场各项有针对性的应急处置措施及落实要求；⑥各级别单位接到事故报告后的应急启动和主要措施；⑦所有单位的应急过程所遵循的指挥与配合原则。 审查的内容包括：①核查现场应急处置方案编制内容是否齐全；②核查施工单位报审时间是否符合要求：在该工程开工之前，施工单位填写专项施工方案报审表，一式三份将现场应急处置方案报总监办审批；③核查现场应急处置方案施工单位内部编制与审核程序合规性。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]