[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105869":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105869,781,1,"单选题","对于施工现场临时用电设备数量在（ ）及以上,或用电设备容量在（ ）及以上的，应监督施工单位编制临时用电专项安全方案。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5台，50kW",true,{"key":16,"text":17,"correct":18},"B","3台，30kW",false,{"key":20,"text":21,"correct":18},"C","5台，30kW",{"key":23,"text":24,"correct":18},"D","3台，100kW","对于施工现场临时用电设备数量在5台及以上,或用电设备容量在50kW及以上的，应监督施工单位编制临时用电专项安全方案。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]