[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105816":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105816,781,1,"单选题","具有以下特点（ ）的路堑高边坡工程，应开展施工安全风险评估",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","25m高土质边坡",true,{"key":16,"text":17,"correct":18},"B","老滑坡体、岩堆体、老错落体等不良地质体地段开挖形成的25m的边坡",false,{"key":20,"text":21,"correct":18},"C","膨胀土、高液限土、冻土、黄土等特殊岩土地段开挖形成的30m的边坡",{"key":23,"text":24,"correct":18},"D","城乡居民居住区、民用军用地下管线分布区、高压铁塔附近等施工场地周边环境复杂地 段开挖形成的25m的边坡。","路堑高边坡工程。 ①高于20m的土质边坡、高于30m的岩质边坡； ②老滑坡体、岩堆体、老错落体等不良地质体地段开挖形成的不足20m的边坡； ③膨胀土、高液限土、冻土、黄土等特殊岩土地段开挖形成的不足20m的边坡； ④城乡居民居住区、民用军用地下管线分布区、高压铁塔附近等施工场地周边环境复杂地段开挖形成的不足20m的边坡。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]