[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105743":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1105743,781,1,"单选题","以下关于工程提前的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人要求承包人提前竣工，应由监理人与承包人共同协商采取加快工程进度的措施和修订合同进度计划",false,{"key":16,"text":17,"correct":14},"B","发包人要求承包人提前竣工，发包人应承担承包人由此增加的费用",{"key":19,"text":20,"correct":21},"C","发包人要求承包人提前竣工，向承包人支付通用合同条款约定的相应奖金",true,{"key":23,"text":24,"correct":14},"D","发包人不得随意要求承包人提前交工","根据《公路工程标准施工招标文件》（2018年版）通用合同条款第11.6条：发包人要求承包人提前竣工，或承包人提出提前竣工的建议能够给发包人带来效益的，应由监理人与承包人共同协商采取加快工程进度的措施和修订合同进度计划。发包人应承担承包人由此增加的费用，并向承包人支付专用合同条款约定的相应奖金。《公路工程标准施工招标文件》（2018年版）公路工程专用合同条款第11.6条：发包人不得随意要求承包人提前交工，承包人也不得随意提出提前交工的建议。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]