[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105741":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105741,781,1,"单选题","以下不属于压缩关键工作持续时间中组织措施的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","增加工作面",false,{"key":16,"text":17,"correct":14},"B","增加关键工作的资源投入",{"key":19,"text":20,"correct":14},"C","增加每天的施工时间",{"key":22,"text":23,"correct":24},"D","采用先进的施工机械",true,"压缩关键工作持续时间的措施中组织措施包括：①增加工作面，组织更多的施工队伍；②增加每天的施工时间（多班制或加班）；③增加关键工作的资源投入（劳力、设备等）。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]