[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105739":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105739,781,1,"单选题","以下不属于每日进度记录内容的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","当日施工停滞的人力、机械数量及其原因",false,{"key":16,"text":17,"correct":14},"B","当日实际完成以及累计完成的工程量",{"key":19,"text":20,"correct":14},"C","当日的天气情况",{"key":22,"text":23,"correct":24},"D","当日的进场人员健康状况",true,"每日进度记录应包括以下内容：①当日实际完成以及累计完成的工程量；②当日实际参加施工的人力、机械数量及生产效率；③当日施工停滞的人力、机械数量及其原因；④当日施工单位的主管及技术人员到达现场的情况；⑤当日发生的影响工程进度的特殊事件或原因；⑥当日的天气情况等。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]