[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105736":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105736,781,1,"单选题","施工单位提交的月进度报告的内容不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","概况或总说明",false,{"key":16,"text":17,"correct":14},"B","工程进度",{"key":19,"text":20,"correct":14},"C","财务状况",{"key":22,"text":23,"correct":24},"D","人员信息",true,"施工单位提交的月进度报告的内容：①概况或总说明：应以纪事方式对计划进度执行情况提出分析；②工程进度：应以工程数量清单所列细目为单位，编制出工程进度累计曲线和完成投资额的进度累计曲线；③工程图片：应显示关键线路上（或主要工程项目上）一些施工活动及进展情况；④财务状况：应主要反映施工单位的现金流动、工程变更、价格调整、索赔工程支付及其他财务支出情况；⑤其他特殊事项：应主要记述影响工程进度或造成延误的因素及解决措施。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]