[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105734":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105734,781,1,"单选题","如果承包人在接到监理人通知后的（ ）天内，未能采取加快工程进度的措施，致使实际工程进度进一步滞后，仍无法按预计工期交工时，监理人应立即通知发包人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","28",{"key":23,"text":24,"correct":14},"D","30","根据《公路工程标准施工招标文件》（2018年版）公路工程专用合同条款第11.5条规定：如果承包人在接到监理人通知后的14天内，未能采取加快工程进度的措施，致使实际工程进度进一步滞后，或承包人虽采取了一些措施，仍无法按预计工期交工时，监理人应立即通知发包人。发包人在向承包人发出书面警告通知14天后，发包人可按第22.1款终止对承包人的雇用，也可将本合同工程中的一部分工作交由其他承包人或其他分包人完成。在不解除本合同规定的承包人责任和义务的同时，承包人应承担因此所增加的一切费用。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]