[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105732":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105732,781,1,"单选题","发包人有权要求承包人相应延长缺陷责任期，但缺陷责任期最长不超过（ ）年。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","4","监理工程师在签发交工证书的同时，应签发《工程缺陷责任证书》，明确缺陷责任期的起止日期。缺陷责任期限由发包人在合同专用条款中确定，由于承包人原因造成某项缺陷或损坏使某项工程或工程设备不能按原定目标使用而需要再次检查、检验和修复的，发包人有权要求承包人相应延长缺陷责任期，但缺陷责任期最长不超过2年。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]