[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105730":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1105730,781,1,"单选题","承包人按约定的合同进度计划在签订合同协议书后（ ）天内，向监理工程师提交合同段总体开工申请。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":21},"C","28",true,{"key":23,"text":24,"correct":14},"D","30","承包人按约定的合同进度计划在签订合同协议书后28天内，向监理工程师提交合同段总体开工申请，其主要内容包括：施工管理机构的建立，劳务、机械设备、材料的进场情况，临时设施修建（包括试验室）完成情况以及合同段总体实施性施工组织设计的提交等。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]