[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105728":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1105728,781,1,"单选题","某工作实施过程中的S曲线如下图所示，图中a和b两点的进度偏差状态是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","a点进度拖后和b点进度拖后",false,{"key":16,"text":17,"correct":14},"B","a点进度拖后和b点进度超前",{"key":19,"text":20,"correct":21},"C","a点进度超前和b点进度拖后",true,{"key":23,"text":24,"correct":14},"D","a点进度超前和b点进度超前","本题考查的是进度监理与进度检查。如果工程实际进展点落在计划S曲线左侧，表明此时实际进度比计划进度超前；如果工程实际进展点落在S计划曲线右侧，表明此时实际进度拖后。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]