[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105726":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105726,781,1,"单选题","总体进度计划的编制应按照（ ）和主要工作横道图分别编绘。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","双代号网络图",false,{"key":16,"text":17,"correct":18},"B","工作横道图",true,{"key":20,"text":21,"correct":14},"C","单代号网络图",{"key":23,"text":24,"correct":14},"D","时标网络图","总体进度计划的编制应按照关键线路网络图和主要工作横道图两种形式分别编绘，并应包括每月预计完成的工作量和形象进度。还可以采用斜条图、进度曲线进行补充。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]