[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105723":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105723,781,1,"单选题","施工进度计划的编制原则不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合理安排施工顺序，保证在劳动力、材料物资以及资金消耗量最少的情况下，按规定工期完成拟建工程施工任务",false,{"key":16,"text":17,"correct":14},"B","采用可靠的施工方法，确保工程项目的施工在连续、稳定、安全、优质、均衡的状态下进行",{"key":19,"text":20,"correct":14},"C","节约施工成本",{"key":22,"text":23,"correct":24},"D","增大利润空间",true,"施工进度计划的编制原则：①合理安排施工顺序，保证在劳动力、材料物资以及资金消耗量最少的情况下，按规定工期完成拟建工程施工任务。②采用可靠的施工方法，确保工程项目的施工在连续、稳定、安全、优质、均衡的状态下进行。③节约施工成本。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]