[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105719":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105719,781,1,"单选题","监理工程师审查计划内容中，施工准备的可靠性不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","所需主要材料和设备的进场计划是否已有保证",false,{"key":16,"text":17,"correct":14},"B","主要骨干人员及施工队伍的进场日期是否已经落实",{"key":19,"text":20,"correct":14},"C","施工测量、材料检查及标准试验的工作是否已经安排",{"key":22,"text":23,"correct":24},"D","建设方资金是否充足",true,"施工准备的可靠性。①所需主要材料和设备的进场计划是否已有保证；②主要骨干人员及施工队伍的进场日期是否已经落实；③施工测量、材料检查及标准试验的工作是否已经安排；④驻地建设、进场道路及供电、供水等是否已经解决或已有可靠的解决方案。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]