[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105717":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1105717,781,1,"单选题","对（ ）进度实施控制是公路工程进度控制的重点。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","方案设计阶段",false,{"key":16,"text":17,"correct":14},"B","施工前期阶段",{"key":19,"text":20,"correct":21},"C","施工阶段",true,{"key":23,"text":24,"correct":14},"D","可行性研究阶段","公路工程施工阶段是工程实体的形成阶段，对施工阶段进度实施控制是公路工程进度控制的重点。监理工程师在施工阶段进度控制就是在保证工程安全和质量的前提下督促承包人按照合同工期完工。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]