[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105713":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105713,781,1,"单选题","（ ）在接到承包人提交的工程进度计划之后，应对进度计划进行认真的审核。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理工程师",true,{"key":16,"text":17,"correct":18},"B","项目经理",false,{"key":20,"text":21,"correct":18},"C","业主",{"key":23,"text":24,"correct":18},"D","建设方负责人","监理工程师在接到承包人提交的工程进度计划之后，应对进度计划进行认真的审核，其目的是检查承包人所制订的工程进度计划是否合理，有无可能实现，是否适合工程的实际条件和现场情况，避免以空洞的、不切实际的工程进度计划来指导施工，造成工期延误。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]