[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105709":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105709,781,1,"单选题","（ ）决定工程的施工顺序、施工方法、资源供应方式、主要指标的控制量等，又是编制网络计划的基础。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可行性研究报告",false,{"key":16,"text":17,"correct":18},"B","施工方案",true,{"key":20,"text":21,"correct":14},"C","设计图纸",{"key":23,"text":24,"correct":14},"D","施工合同","施工方案决定工程的施工顺序、施工方法、资源供应方式、主要指标的控制量等，又是编制网络计划的基础。编制网络计划既要符合施工工艺和技术上的要求，又要符合目前的施工技术和组织管理水平，以保证工程质量，有利于提高施工效率、缩短工期、降低成本。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]