[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105707":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105707,781,1,"单选题","以下属于工程直接成本的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","规费",false,{"key":16,"text":17,"correct":14},"B","财务费用",{"key":19,"text":20,"correct":14},"C","企业管理费用",{"key":22,"text":23,"correct":24},"D","机械使用费",true,"工程直接成本是指完成某一建设项目的施工任务而直接消耗在工程上的费用，即直接使生产资料转移而形成工程实体所投入的费用。它包括消耗在施工中的人工费、材料费、机械使用费和其他直接费以及现场经费，而其他直接费有冬季施工增加费、雨季施工增加费、夜间施工增加费、高原地区施工增加费等。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]