[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105706":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105706,781,1,"单选题","下列资源安排的方式中，目的是寻求工程网络计划资源优化的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","资源使用量最小条件下的合理工期安排",false,{"key":16,"text":17,"correct":14},"B","资源均衡使用条件下的最短工期安排",{"key":19,"text":20,"correct":14},"C","工程总成本最低条件下的资源均衡安排",{"key":22,"text":23,"correct":24},"D","工期固定条件下的资源均衡安排",true,"资源优化的目的是通过改变工作的开始时间和完成时间，使资源按照时间的分布符合优化目标。工程网络计划资源优化有两种方式：①资源有限，工期最短；②工期固定，资源均衡。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]