[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105704":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105704,781,1,"单选题","网络计划时间优化的基本方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","从前往后法",false,{"key":16,"text":17,"correct":18},"B","循环优化法",true,{"key":20,"text":21,"correct":14},"C","从后往前法",{"key":23,"text":24,"correct":14},"D","单向优化法","网络计划时间优化的基本方法是循环优化法。缩短工期的着眼点是关键线路，因此必须从关键线路入手。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]