[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105702":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105702,781,1,"单选题","时间优化措施不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","调整施工组织",false,{"key":16,"text":17,"correct":14},"B","压缩关键工作持续时间",{"key":19,"text":20,"correct":14},"C","计划外增加资源",{"key":22,"text":23,"correct":24},"D","压缩重点部位的工作时间",true,"网络计划的工期取决于关键线路上工作持续时间之和，因此，缩短关键工作的持续时间是网络计划时间优化的基本思路之一。它以关键线路为研究对象，选择合理的工期缩短方案，从而避免盲目加快施工进度可能造成的浪费现象，并获得时间最优的效果。在网络计划的时间优化中，缩短工期主要是通过调整施工组织、压缩关键工作持续时间和计划外增加资源等措施来实现的。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]