[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105692":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105692,781,1,"单选题","当初始网络计划的计划工期与指令工期差值不大时，可采用（ ）法缩短工期。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","平均加快关键工作持续时间",true,{"key":16,"text":17,"correct":18},"B","依次压缩关键工作持续时间",false,{"key":20,"text":21,"correct":18},"C","选择压缩关键工作持续时间",{"key":23,"text":24,"correct":18},"D","加权平均加快关键工作持续时间","当初始网络计划的计划工期与指令工期差值不大时，可采用平均加快关键工作持续时间法；当计划工期与指令工期相差较大时，通常按施工工艺要求，并根据技术可行、经济合理原则，事先选择若干项关键工作来压缩其工作持续时间；选择缩短法是在网络计划的关键线路上有的放矢地选择某些工作来缩短其作业持续时间。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]