[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105688":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105688,781,1,"单选题","以下关于关键线路特性的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键线路上各工作的自由时差均为零",true,{"key":16,"text":17,"correct":18},"B","关键线路是从网络计划起点到终点之间持续时间最长的线路",false,{"key":20,"text":21,"correct":18},"C","关键线路在网络计划中不一定只有一条，有时存在多条",{"key":23,"text":24,"correct":18},"D","非关键工作如果使用了总时差，就会转化为关键工作","关键线路的特性：①关键线路上各工作的总时差均为零；②关键线路是从网络计划起点到终点之间持续时间最长的线路；③关键线路在网络计划中不一定只有一条，有时存在多条；④非关键工作如果使用了总时差，就会转化为关键工作⑤当非关键线延长的时间超过它的总时差，关键线路就转变成为非关键线路。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]