[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105686":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105686,781,1,"单选题","网络计划技术是一种（ ）分析方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定性",false,{"key":16,"text":17,"correct":18},"B","定量",true,{"key":20,"text":21,"correct":14},"C","综合",{"key":23,"text":24,"correct":14},"D","模糊","正确地绘制代表工程项目进度计划的双代号网络图，只是把工程项目工作之间的逻辑关系用网络计划的形式表达出来了。网络计划技术是一种定量分析方法，它可以为工程计划管理提供一系列重要的定量信息，而这些定量信息是通过网络计划图时间参数计算以后获得的。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]