[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105685":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105685,781,1,"单选题","双代号网络图应符合（ ）原则。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","只有一个终点节点",true,{"key":16,"text":17,"correct":18},"B","只有一个开始工作",false,{"key":20,"text":21,"correct":18},"C","起点节点可有多条内向箭线",{"key":23,"text":24,"correct":18},"D","终点节点可有多条外向箭线","双代号网络图只有一个起点节点和一个终点节点（任务中部分工作需要分期完成的网络计划除外）。除网络图的起点节点和终点节点外，不允许出现没有外向箭线的节点和没有内向箭线的节点。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]