[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105683":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105683,781,1,"单选题","双代号网络计划的网络图的三要素不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","箭线",false,{"key":16,"text":17,"correct":14},"B","节点",{"key":19,"text":20,"correct":14},"C","流",{"key":22,"text":23,"correct":24},"D","工作",true,"双代号网络计划是目前应用较为普遍的一种网络计划形式。利用网络技术表示一项工程任务或一个计划中各项工作的先后、衔接关系和所需时间及其他资源的工作流程图，就称为网络计划图，双代号网络计划的网络图是由三个要素组成的，即箭线、节点和流。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]