[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105681":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105681,781,1,"单选题","某工程网络计划中，工作M的持续时间为4天，工作M的三项紧后工作的最迟、开始时间分别为第21天、第18天和第15天，则工作M的最迟开始时间是第（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","11",true,{"key":16,"text":17,"correct":18},"B","14",false,{"key":20,"text":21,"correct":18},"C","15",{"key":23,"text":24,"correct":18},"D","17","对于有紧后工作的工作，M工作的最迟完成时间应等于其紧后工作最迟开始时间的最小值15天，M工作的最迟开始时间＝15－4＝11（天）。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]