[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105679":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1105679,781,1,"单选题","某工程单代号搭接网络计划中工作 B、 D、E之间的搭接关系和时间参数如图10-4-1所示。工作D和工作E的总时差分别为6天和2天，则工作B的总时差为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","8",{"key":19,"text":20,"correct":21},"C","9",true,{"key":23,"text":24,"correct":14},"D","2","工作的总时差TF是指，在不影响总工期的前提下，本工作可以利用的机动时间。在单代号网络计划中，工作的总时差应等于本工作与其各紧后工作之间的时间间隔加该紧后工作的总时差所得之和的最小值，即TFi＝min{LAGi，j＋TFj}＝min{3＋6，8＋2}＝min{9，10}＝9（天）。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]