[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105677":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105677,781,1,"单选题","某分部工程中各项工作间逻辑关系见表10-1-1，相应的双代号网络计划如图10-1-1所示，图中错误有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","多个终点节点",false,{"key":16,"text":17,"correct":18},"B","多个起点节点",true,{"key":20,"text":21,"correct":14},"C","工作代号重复",{"key":23,"text":24,"correct":14},"D","存在循环回路","根据图10-1-1，只有箭尾没有箭头的节点可以判定为起点节点，B项，有两个起点节点①、②。此外，还存在以下问题：①G的紧后工作应为I、J，而实际只有J；节点⑤、⑥应互换。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]