[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105675":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105675,781,1,"单选题","计算网络计划时间参数的目的之一是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","得到总工期",false,{"key":16,"text":17,"correct":18},"B","找出计划中的关键线路",true,{"key":20,"text":21,"correct":14},"C","掌握施工进度",{"key":23,"text":24,"correct":14},"D","控制时间节点","计算网络计划时间参数的目的之一是找出计划中的关键线路。找出了关键线路也就抓住了工程进度计划的主要矛盾，这样就可使工程管理人员在施工的组织和管理工作中做到心中有数。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]