[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105671":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105671,781,1,"单选题","关于单代号网络中关键线路确定的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单代号网络计划图中确定关键线路的方法与双代号网络计划图基本相同",false,{"key":16,"text":17,"correct":18},"B","单代号网络计划图中可用关键节点法来确定关键线路",true,{"key":20,"text":21,"correct":14},"C","单代号网络计划图中主要采用关键工作法确定关键线路",{"key":23,"text":24,"correct":14},"D","连接工作总时差为零的关键工作自始至终的线路就是关键线路","单代号网络计划图中确定关键线路的方法与双代号网络计划图基本相同，但由于单代号网络图没有节点时间参数计算，所以不存在用关键节点法来确定关键线路。因此，单代号网络图主要采用关键工作法确定关键线路，即连接工作总时差为零的关键工作自始至终的线路就是关键线路。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]