[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105669":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1105669,781,1,"单选题","关于单代号网络图时间参数计算的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","计算工作的最早可能开始时间应从网络图起点开始",false,{"key":16,"text":17,"correct":14},"B","计算工作的最迟时间应从网络图的终点开始",{"key":19,"text":20,"correct":21},"C","工作总时差的概念与双代号网络图不完全相同",true,{"key":23,"text":24,"correct":14},"D","由于单代号网络计划图中用节点表示工作，所以它只有工作时间参数的计算，而不存在节点时间参数的计算","在单代号网络计算图中，工作总时差的概念与双代号网络图完全相同。单代号网络图中工作的局部时差概念也与双代号网络图相同。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]