[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105667":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105667,781,1,"单选题","关于单代号网络计划图的基本符号的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单代号网络计划图中，一个节点表示一项具体的工作，只能用圆圈表示",true,{"key":16,"text":17,"correct":18},"B","单代号网络计划图中节点表达工作，与双代号网络计划图中箭线表示工作一样",false,{"key":20,"text":21,"correct":18},"C","在单代号网络计划图中，箭线表示工作之间的相互关系，不占用时间，也不消耗资源",{"key":23,"text":24,"correct":18},"D","在单代号网络计划图中，一项工作只有一个代号，不得有重复代号","单代号网络计划图中，一个节点表示一项具体的工作，它可以用圆圈或方框表示。节点所表达工作的名称、持续时间和代号一般都标注在圆圈或方框内。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]