[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105662":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105662,781,1,"单选题","单代号网络图与双代号网络图的区别仅在于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","时间参数计算规则",false,{"key":16,"text":17,"correct":18},"B","图形表达符号",true,{"key":20,"text":21,"correct":14},"C","关键路线表达",{"key":23,"text":24,"correct":14},"D","进度计划内容","由于单代号网络图与双代号网络图的区别仅在于图形表达符号不同，而表达进度计划的内容是相同的，所以绘制双代号网络图的基本规则，在单代号网络图绘制中都应遵守。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]