[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105660":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105660,781,1,"单选题","（ ）一般用于控制整个计划的总工期。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自由时差",false,{"key":16,"text":17,"correct":18},"B","总时差",true,{"key":20,"text":21,"correct":14},"C","最早开始时间",{"key":23,"text":24,"correct":14},"D","最迟开始时间","工作的总时差具有以下性质： ①如果工作的总时差TF（i，j）＝0，则工作（i，j）为无任何机动时间使用的关键工作； ②总时差不但属于本工作，而且与前后工作都有关系，它是一条线路所共有的最大机动时间； ③工作的总时差一般用于控制整个计划的总工期。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]