[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105658":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105658,781,1,"单选题","工作A的工作持续时间为3天，该工作有三项紧后工作，工作持续时间分别为4天、6天、3天；最迟完成时间分别为第16天、12天、11天，则工作A的最迟开始时间为第（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6",false,{"key":16,"text":17,"correct":18},"B","3",true,{"key":20,"text":21,"correct":14},"C","8",{"key":23,"text":24,"correct":14},"D","12","本题考查的是时间参数的计算及关键线路。工作的最迟完成时间=所有紧后工作最迟开始时间的最小值，工作的最迟开始时间=工作的最迟完成时间－工作持续时间，工作A的最迟开始时间=min{（16－4），（12－6），（11－3）}－3=3（天）。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]