[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105656":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105656,781,1,"单选题","在工程网络图中，工作K的最迟完成时间为第20天，其持续时间为6天，该工作有三项紧前工作，它们的最早完成时间分别为第8天、第10天、第12天，则工作K的总时差为（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","8",false,{"key":16,"text":17,"correct":14},"B","6",{"key":19,"text":20,"correct":14},"C","4",{"key":22,"text":23,"correct":24},"D","2",true,"本题考查的是时间参数的计算及关键线路。工作的总时差等于该工作最迟完成时间与最早完成时间之差，或该工作最迟开始时间与最早开始时间之差。K工作的总时差＝20－6－max{8，10，12}＝2（天）",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]