[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105654":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105654,781,1,"单选题","在工程网络计划中，某项工作的自由时差不会超过该工作的（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总时距",false,{"key":16,"text":17,"correct":14},"B","持续时间",{"key":19,"text":20,"correct":14},"C","间歇时间",{"key":22,"text":23,"correct":24},"D","总时差",true,"本题考查的是时间参数的计算及关键线路。对于同一项工作而言，自由时差不会超过总时差。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]