[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105653":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105653,781,1,"单选题","在工程网络计划中，（ ）是指在不影响总工期的前提下，本工作可以利用的机动时间。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","时间间隔",false,{"key":16,"text":17,"correct":18},"B","总时差",true,{"key":20,"text":21,"correct":14},"C","自由时差",{"key":23,"text":24,"correct":14},"D","时距","本题考查的是时间参数的计算及关键线路。工作的总时差是指在不影响任何一项紧后工作的最迟必须开始时间的条件下，工作所拥有的最大机动时间。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]