[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105651":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1105651,781,1,"单选题","在不影响其紧后工作最早开始时间的前提下，本工作可利用的机动时间为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","总时差",false,{"key":16,"text":17,"correct":14},"B","最迟开始时间",{"key":19,"text":20,"correct":21},"C","自由时差",true,{"key":23,"text":24,"correct":14},"D","最迟完成时间","本题考查的是时间参数的计算及关键线路。工作的局部时差，是在不影响任何一项紧后工作最早可能开始时间的条件下，本工作所具有的机动时间。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]